  • R01

    Supply point associated with the CUPS does not exist.

  • R02

    No prior ATR contract in force.

  • R03

    NIF/CIF does not match the NIF/CIF on the contract in force.

  • R06

    A prior ATR request is already in progress.

  • R07

    Contract type is not provided or is invalid.

  • R08

    Contract end date is not provided or is invalid.

  • R09

    A court judgment relating to the customer's debt exists.

  • R11

    Incorrect retailer.

  • R12

    Contract cut off for non-payment.

  • R14

    Requested power exceeds the maximum authorised power at low voltage.

  • R15

    Incorrect power sequence: Pi > Pi+1.

  • R17

    Tariff is not valid for the supply voltage.

  • R18

    New customer-owned equipment does not meet ATR contracting criteria.

  • R20

    Installation unavailable or supply expansion in progress (open docket, docket code, and docket reason).

  • R21

    A prior contract is already in force.

  • R22

    Requested power exceeds the maximum recognised extension power.

  • R23

    CNAE is not provided or is invalid.

  • R26

    Access blocked more than twice for reasons beyond the distributor's control.

  • R27

    ICP box is invalid or does not exist.

  • R28

    Rejection due to anomaly.

  • R29

    Customer equipment missing.

  • R31

    Holder's objection.

  • R32

    Essential supply.

  • R34

    Customer cannot be disconnected by court or administrative order.

  • R35

    Customer already disconnected.

  • R36

    Incorrect NIF/CIF.

  • R37

    A prior A3 request is already in progress.

  • R38

    A prior C1 request is already in progress.

  • R39

    A prior C2 request is already in progress.

  • R40

    A prior M1 request is already in progress.

  • R42

    Cancellation is not possible: work order already in the field or non-cancellable actions within a claim.

  • R43

    Cancellation is not possible: request already activated.

  • R46

    Requested operation date is retroactive.

  • R47

    Power values not normalised for a three-phase supply.

  • R48

    Power values not normalised for a single-phase supply.

  • R49

    Voltage change from single-phase to three-phase is required.

  • R50

    Measurement transformers out of range.

  • R52

    Tariff is not valid for the requested power.

  • R53

    A connection docket must be opened.

  • R54

    Temporary bulletin does not exist.

  • R55

    New customer is the same as the current customer.

  • R56

    Field 84 data missing in modification.

  • R57

    Low-voltage technical documentation is missing.

  • R58

    Contact phone number is missing.

  • R59

    Cabinet/module is invalid or does not exist.

  • R60

    Installation is incomplete or contains invalid elements.

  • R61

    CGP is invalid or does not exist.

  • R62

    Action requested by the retailer does not match the customer's requirements.

  • R63

    Requested power cannot be less than the BIE power (non-interruptible Mode 2 supplies).

  • R64

    Disconnection is not technically possible at the cut-off point.

  • R65

    More than one power modification at a supply point within 12 months for the same supply point holder.

  • R66

    Remote-managed supply.

  • R67

    Supply with maximum demand meter.

  • R68

    Not permitted for a free-market retailer.

  • R69

    The distributor disagrees.

  • R70

    Retailer is disabled.

  • R71

    Multiple contracts exist for the same supply point.

  • R72

    Contract cancelled.

  • R73

    Supply with power greater than 15 kW.

  • R74

    Supply with more than one meter.

  • R75

    Discrepancy between reading information and number of integrators.

  • R76

    More digits than number of meter wheels.

  • R77

    Reading is lower than the last actual reading.

  • R78

    Excessive consumption.

  • R79

    Reading period is too short.

  • R80

    Supply with maximum demand meter and/or reactive energy.

  • R83

    Energy poverty.

  • R84

    Duplicate claim.

  • R85

    Mandatory field 'xxxx' missing.

  • R86

    Connection docket code is incorrect.

  • R87

    Invoice does not exist.

  • R88

    Invoice is not remotely managed.

  • R89

    No best available curve (no curve generated).

  • R90

    Self-consumption type 1 or 2B: consumption holder does not match the installation holder.

  • R91

    Self-consumption: associated contract request is missing.

  • R92

    Self-consumption: the self-consumption category in the request does not match the one registered at the distributor.

  • R93

    Self-consumption: self-consumption type is invalid.

  • R94

    Self-consumption: impossible to process request for this supply point.

  • R95

    Self-consumption: requested modality does not match the technical contract.

  • R96

    Self-consumption: contracted power exceeds 100 kW.

  • R97

    Self-consumption: contracted power is less than the installed generation power.

  • R98

    Self-consumption: minimum permanence period in self-consumption modality not respected.

  • R99

    Other.

  • RA1

    Unresolved incidence.

  • RA2

    Contract cut off by the distributor.

  • RA3

    Dangerous installation.

  • RA4

    Rejection of the retailer's request.

  • RA5

    Power above/below the contract type.

  • RA6

    Requested power differs from the authorised power.

  • RA7

    Authorisation date has expired.

  • RA8

    Ministerial authorisation required.

  • RA9

    Requested power exceeds the maximum authorised power at high voltage.

  • RB1

    High-voltage technical documentation is missing.

  • RB2

    Rejection due to confirmed fraud.

  • RB3

    Supply point not located.

  • RB4

    Retailer outside its geographic area.

  • RB5

    A prior B1 request (reason 01) is already in progress.

  • RB6

    A prior B1 request (reason 02) is already in progress.

  • RB7

    A prior B1 request (reason 03) is already in progress.

  • RB8

    A prior B1 request (reason 04) is already in progress.

  • RB9

    An in-progress non-cancellable deregistration-for-non-payment B1 request exists (reasons 01, 02 if the COR has rejected the transfer and work has already started to deregister, 04, or reason 03 during the process of terminating the access contract).

  • RC1

    Concurrence with a retailer change/COR transfer/holder change by transfer. The change activation takes priority over the termination.

  • RC2

    Reconnection not technically possible.

  • RC3

    Retailer in the process of being disabled.

  • RC4

    Disconnection not technically possible due to hazard.

  • RC5

    It is not possible to request a change/modification/registration/deregistration at a fixed date more than 30 calendar days in advance.

  • RC6

    Express objection from the holder on site. Documentation attached.

  • RC7

    Holder's impediment. Initiate the fraud process if applicable.

  • RC8

    Supply suspension rejected due to concurrence with deregistration for non-payment.

  • RC9

    Docket is incorrect or does not exist.

  • RD1

    Supply eligible for social bonus.

  • RD2

    Cancellation is not possible: no prior request exists.

  • RD3

    Does not comply with the normalised power or the established power multiple for the supply point.

  • RD4

    The requested voltage type is the same as the supply point's current type.

  • RD5

    Documentation missing as required by Law 12/2017 of the Balearic Islands.

  • RD6

    Holder of the underlying process does not match the holder seeking to withdraw.

  • RD7

    Withdrawal from an ongoing contracting process.

  • RD8

    Withdrawal not technically possible on site.

  • RD9

    Withdrawal not possible due to a subsequent contracting action.

  • RE1

    Reference request code does not exist at the distributor.

  • RE2

    The withdrawal does not apply to the underlying process.

  • RE3

    Withdrawal requested by a legal entity.

  • RE4

    Previous non-payment.

  • RE5

    CUPS subject to data protection legislation.

  • RE6

    Self-consumption type modification not permitted: fewer than four months have elapsed since the last modification.

  • RE7

    Distribution agreement and/or coefficients file is missing or incorrect; distribution coefficients are missing from the file.

  • RE8

    Technical information from the regional authority not received (for LV and <100 kW).

  • RE9

    The remaining modification requests for the collective have not been received within the established period.

  • RF1

    Consumer disagrees with the self-consumption information.

  • RG1

    Only the following can be modified: the identifier type and identifier, or the name and surname(s)/company name.

  • RG2

    Incorrect internal inspection; technical documentation after the inspection must be provided.

  • RG3

    Prior ATR request/claim code does not exist.

  • RG4

    Minimum vital supply.

  • RG5

    Modification applies to a social bonus.

  • RG6

    It is not possible to modify the distribution agreement or coefficients file if fewer than four months have elapsed since the last modification.

  • RG7

    If the ancillary services are not negligible and a single contract is registered, the installation type cannot be '03' (adjacent via network).

  • RG8

    The self-consumption modification request matches the contract in force.

  • RG9

    The modification request cannot incorporate other technical modifications.

  • RH1

    Self-consumption type is invalid.

  • RH2

    Subsection type is invalid.

  • RH3

    Collective self-consumption.

  • RH4

    The customer's installation cannot export energy to the network.

  • RH5

    A second power modification cannot be requested within the same billing cycle.

  • RH6

    The power reduction does not meet the requirements of Article 7 of RDL 18/2022.

  • RH7

    Self-consumption documentation is missing.

  • RH8

    In-flight agreement change.

  • RH9

    Request already submitted by another party.

  • RI1

    Holder of the underlying process does not match the holder seeking reinstatement.

  • RI2

    Reinstatement requested for installations above 1 kV.

  • RI3

    Reinstatement does not apply to the underlying process.

  • RI4

    Reinstatement not technically possible on site.

  • RI5

    Reinstatement not possible due to a subsequent contracting action.

  • RI6

    Reinstatement request exceeds the maximum period of one year.

  • RI7

    Concurrence with a reinstatement process; reinstatement activation takes priority.

  • RI8

    A prior in-progress request exists.

  • RJ1

    The contract to be reinstated has expired.

  • RJ2

    Documentary evidence is available.

  • RJ3

    Reinstatement rejected without a specific reason.

  • RJ4

    Requested technical modification matches the prior one at the distributor.

  • RJ5

    Incoming retailer rejects the reinstatement.

  • RJ6

    Reinstatement on an in-progress retailer change.

The example data in the variables and responses below are autogenerated values designed to resemble real inputs. They do not represent actual customer data, and in some cases may require additional validation.

Example

"R01"